Field notes: 60 sensors in a Mirabel warehouse, in two phases
Multimedia Gears
Aug 21, 2026
7 mins

Peak demand charges and conveyors that stopped without warning
A distribution centre in Mirabel was paying for demand peaks it could not see and losing hours to conveyor stoppages nobody predicted.
Energy meters by zone, in two weeks
Clamp meters on the main feeds and the forklift chargers, one gateway per zone, a dashboard by the end of week two. The peak showed up immediately: all the forklifts charging at shift change.
Vibration on the conveyors, in four weeks
With the energy data flowing, we added vibration sensors on the conveyor drives and built a two-week baseline for each before enabling alerts.
14% lower peak, two failures caught early
Staggering the charging schedule cut the monthly peak by 14%. The vibration alerts have caught two bearing failures before they stopped a line.
“Energy first, vibration second. The order mattered more than the hardware.
Karim Haddad IIOT ENGINEER
What to do next
Tell us what you need to see, show or measure. We reply within 48 hours with a written scope and a fixed quote.

Let’s plan your next project
Tell us what you need to see, show or measure. We reply with a written scope and a fixed quote, typically within 48 hours.